ARIES Program
Public Information Site
 
 
 
 

ARIES Documents

Utility Advisory Committee Reports

Minutes of the Fifth Meeting (October 13-14, 1994, UC San Diego)

Power Plant Studies Utility Advisory Committee, and EPRI Fusion Working Group

INTRODUCTION

Dean Robert W. Conn opened the combined Utility Advisory Committee/EPRI Fusion Working Group Meeting, hosted by UC San Diego, by welcoming all attendees. He introduced Dr. Robert Iotti of Raytheon Engineers and Constructors, who recently has been appointed as Administrative Officer to the ITER Joint Central Team, to review the status of ITER.

ITER UPDATE

Dr. Iotti explained that his first and most important duty was to make sure that the routine management processes were in place at the Joint Central Team work sites and are working smoothly. After that, those management processes that are unique to ITER and the technical issues will be addressed.

Dr. Iotti reviewed the status of ITER. He noted the significant change in management style that had occurred recently within the ITER Joint Central Team, towards a more team-oriented style which would better fit the current stage of the project. He remarked that the previous management appeared to have been criticized unduly, and that the previous manner of operation was probably necessary during Protocol 1 since the goal was to make rapid progress towards defining a conceptual design basis.

Critical topics that will receive much greater attention and input as the design evolves include safety and remote maintenance. Other critical issues requiring further design modifications are the magnets, divertor, and first wall and blanket. It appeared that in the technical areas, not all of the requirements had been clearly identified or correctly ranked. For instance, the performance of the device had been the principal driver of the design, while safety now will assume a much higher priority with remote handling requirements, rather than solely performance driving the design details to a greater extent. The designs of several systems are being re-examined to assure that the selected design approach is appropriate. The items that are being re-examined include the toroidal field (TF) coils, the choice of poloidal field (PF) superconducting materials, the coil case design, the addition of another PF coil, the remote handling aspects of the vacuum vessel, the divertor armor material, a closer-fitting cryostat, and the tradeoff between plasma control and reactive power.

The chairman of the joint committees, Steve Rosen, commented on the very high post-shutdown dose rates within the ITER torus and asked if the predicted value of 1x106 R/h radiation level at shutdown inside the torus is correct. Both Dr. Iotti and Dr. Conn affirmed the nominal level is expected to be 3x106 R/h within 24 h after shutdown, and that the level would remain high for years. This is due to the choice of stainless steel as the vessel structural material. Vanadium and silicon carbide (SiC) composites would significantly reduce the level of the post-shutdown radiation and its half life, but would not eliminate the need for remote handling operation inside the torus. These low-activation materials, vanadium and SiC composites, are not being used because there is insufficient engineering data available to define their characteristics in the fusion environment. Large scale manufacturing and fabrication techniques still must be developed, and engineering codes (similar to ASME codes) are still to be developed. Thus the structural material of the vessel must be stainless steel or the project would have to be delayed until sufficient data becomes available.

Historically, it has taken decades to develop an acceptable database and sufficient fabrication experience for the design of a Demo power plant. The ensuing discussion resulted in general agreement that advanced materials will be needed in order to make a tokamak attractive to a utility. ITER must give the utilities the confidence that it will help support the rationale for Demo.

Bob Conn explained that the physics goals will be demonstrated in the Basic Performance Phase (BPP) of ITER. In the following phase, called the Extended Performance Phase (EPP), a number of advanced breeding blanket modules will be tested in ITER. Prior to this, a neutron-source materials test facility is planned to provide sufficient test results for candidate materials to enable confident design, fabrication, and operation of full-sized modules in the ITER EPP phase. It was indicated that the ITER EPP phase could "qualify" first walls, blankets, and divertors, though a final conclusion on this cannot yet be made.

Given the current pace of effort on advanced materials testing and the tight schedule for Demo, there appeared to be some weaknesses in the development plan. For example, there was no indication that the materials test results would flow into ITER before they were used in Demo design. Some concern expressed by the Advisory Committee prompted the scheduling of presentations on the topic of develoment pathways during the next meeting.

Another conclusion was that, unless there is an early and strong fusion materials development program together with the construction of an appropriate test facility or facilities, the currently planned Demo will not be viewed as a true Demo by the utilities. It appears clear that ITER alone does not allow proceeding directly to Demo. Dean Conn and Dr. Iotti explained that the current DOE and ITER strategy does call for an advanced materials test facility. The use of an advanced materials test facility, in combination with limited component testing during the "extended performance phase" of ITER, could still lead to the fusion Demo after ITER.

Dr. Iotti discussed the on-going regulatory and licensing efforts for ITER. Several committees and working groups are trying to define approaches and frameworks to streamline the process, while assuming the promise of a safe and clean energy source. It is clear that ITER requirements will be more severe than those envisioned for Demo and the follow-on commercial fusion power plants. It is essential that ITER not set overly restrictive licensing and regulatory precedents for subsequent fusion generating plants.

UPDATE FROM DOE

Al Opdenaker, Office of Fusion Energy, provided an overview of the U.S. fusion program. He reviewed the current budget for OFE and outlined some of the recent Congressional legislation which may impact the future direction of the U.S. fusion program. ITER siting issues were raised, and the question of U.S. interest (and commitment) was discussed in the event that ITER is sited elsewhere. Specifically, the Committee asked if the U.S. wants ITER to be sited in the U.S. Al Opdenaker responded that no decision has been made. Dean Conn explained that acquiring the site for ITER may not be quite as desirable as previously thought. An alternate premise that is now viable is that, with the advent of higher quality communications, the experiments in ITER could be conducted from remote sites. It is entirely possible that there will be fewer scientists at the actual site than first thought and more scientists at distributed sites. This would modify the economic assumptions that had been considered so far as well as the anticipated technical benefits arising from the economic contributions.

Various advisory and review committees have been formed and are expected to assess the U.S. fusion program during the next few months. Of particular note is the reconstitution of the Fusion Energy Advisory Committee (FEAC) following an extended dormancy. Dean Conn will again assume the chairmanship. Steve Rosen will be a member. The majority of the membership will be persons from technical fields other than fusion and from industry. Previously the membership consisted primarily of persons from within the fusion community.

ITER ECONOMIC STUDY

Ken Wilson reported the results of an ITER Economic Study on ITER siting that had been undertaken by Argonne National Laboratory with the assistance of external economic experts. The study addressed the national economic benefits to the U.S., and the benefits to the local community, of siting the ITER within the U.S. or elsewhere. The construction period was assumed to be 8 years at a total cost of $10B, followed by an operating period of 18 years at a total cost of $8.6B, with a further $1B being required for decommissioning, for a total lifetime cost of $19.6B. An analysis based upon these assumptions concluded that the host party would incur 40% of the total cost. Of the remaining 60% of the cost, 42% would be spent by non-host parties within their local economies, and 18% would be spent by non-host parties at the host site. There would be a very small benefit to the U.S. economy overall through siting ITER in the U.S., and a small negative impact if ITER were sited elsewhere. On the other hand, the benefits to the local community in which ITER is sited will be enormous. Peak host employment by ITER itself is estimated at 3,000 during construction (with 11,000 total additional jobs being generated in the local area) and at 900 during operation (with 4,000 total additional jobs in the local area). The study did not, however, take into account any spin-offs that might arise from ITER, nor did it consider what alternative benefits might arise if the money was not spent on ITER but was spent on some other major project instead.

A new paradigm for international participation in ITER that had been suggested by Dean Conn, in which many of the scientists and their support staff would remain in their home country and interact effectively through advanced telecommunications methods, would tend to reduce the incentive to host ITER.

FIRST-OF-A-KIND FACILITIES

Larry Papay of Bechtel discussed his experiences with first-of-a-kind energy generation facilities and surveyed first-of-a-kind startup problems in several related technologies involving facilities such as Clinch River, Cool Water, Solar Two, and Superconducting Magnetic Energy Storage (SMES). Approaches to forming consortia to build and operate a Demo were discussed. It was emphasized that DOE must convince the utilities and industries to participate early in the project to ensure that their own specific needs are satisfied and competent engineering firms are available to build the fusion Demo. Having the right project scope, plant size, and adequate funding are critical.

Dr. Papay thought that industry would be the likely project leaders, and that government, industry and utilities would fund the project through some form of cost sharing. Ideas for cost indemnification were discussed, based upon the assumption that utilities would only participate in Demo if there was a clear financial incentive to do so. For example, if the cost of Demo was 1.2 times the prevailing cost of electricty (COE), but the U.S. Government subsidized 50% of the cost, a utility might be willing to take the risk if it felt there was a reasonable probability of a positive financial return on its investment. Additional (financial) participation from the private sector, an industrial consortium say, might be expected if the investment was seen to place the consortium in a strong position to win future orders. Such a consortium might comprise a number of industrial vendors, A&Es, and utilities. Governmental assistance could take the form of direct funding, funding guarantees, guaranteed (or forgiven) loans, or favorable tax incentives. The possibility of a single vendor stepping forward and assuming a major portion of the $4B of industrial funding that would be required to construct Demo was discussed. Although a single vendor would be preferred, the consensus was that the financial risk was too large for any one company to assume. Betting one's company on the success of Demo would present too much of a risk based upon today's knowledge.

The preferred size of Demo was discussed. Although there was a previous successful program in which a demonstration unit rated at 10% of the required commercial size was constructed and operated, a fusion generator this small was not thought to be realistic for subsequent scaling to full size with low risk. The feasible size for a demonstration fusion power plant was thought to lie within the range of 30% to 80% of the required size of the commercial system. This scenario balances a lower capital cost and a less profitable Demo against a higher capital cost, a lower scalability risk, and a more profitable Demo. Other unknowns involve the nature of the future energy market, the public perception of energy options, and Federal legislation and regulations that will change relationships within the energy community.

REMOTE HANDLING TECHNOLOGIES

Tom Burgess reviewed the remote handling technologies associated with TFTR and JET and those being planned for ITER. Some of the manipulator systems in use are extremely sophisticated, having as many as 28 degrees of freedom. In general, these systems are extremely complex and often require long down-times for replacement of even very small components. Existing maintenance schemes clearly have been designed "a posteriori", much later than the design of the basic tokamak itself.

Dr. Burgess described the evolving ITER Remote Handling requirements and systems. Radiation doses of 3x106 R/h are expected as a remote handling environment in the torus interior. Some ITER components (for example the first wall, blanket, and divertor modules) are scheduled for regular replacement. Other components (for example the cryostat and magnets) should not require replacement during the entire life of the plant. In-torus remote handling is to be accomplished at atmospheric pressure. Dr. Burgess described some of the maintenance steps for ITER. All ITER components are being designed to be removed and replaced remotely. For example, the divertor segment replacement scheme requires the removal of up to four neighboring segments. Most of the maintenance operations will be performed through small openings, and require the use of either cantilevered arms or rail systems.

Steve Rosen remarked that remote handling is one of the most serious concerns of the committee. Dr. Wilson reminded the audience that Dr. Iotti had acknowledged the lack of consideration of remote handling in the earlier design, and had expressed the firm intent to raise this issue to the forefront. Dr. Najmabadi stated that commercial power plant remote handling systems would be very different from these currently being designed for ITER, and explained a potential maintenance scheme that had been developed during the ARIES study. By taking advantage of the smaller plasma, fewer coils, and a novel cryostat design, it was possible to place the TF coils far enough away from the in-vessel components such that simple horizontal removal of entire segments became possible on rails. In this instance, a stand-by segment would be inserted quickly, and problems of the removed segment would be repaired away from the fusion device.

Ken Wilson affirmed that, although stainless steel will be used as the first-wall and blanket structural material in the Basic Performance Phase of ITER, test modules of vanadium and liquid lithium will be available for evaluation in the Engineering Performance Phase. This emphasized the need to develop an advanced materials data base for the fusion environment with adequate fluence to predict the end-of-life performance. Additionally, there will be a need to validate component performance prior to the ITER Extended Performance Phase, perhaps through small scale testing during the ITER Basic Performance Phase or via testing in a separate volume neutron source.

REAL AND REACTIVE POWER REQUIREMENTS

Charles Neumeyer of Raytheon Engineers and Constructors presented the current ITER active and reactive power requirements. The cycling poloidal field coils require 3,500 MVA for operation. The final power requirements are being developed to minimize the impact on the local utility that supplies the power. High power demands for short time periods may pull down grid voltage and frequency to unacceptable levels unless some modifications to the ITER requirements are made.

TFTR: HISTORY AND RECENT RESULTS

Dr. Dale Meade of Princeton Plasma Physics Laboratory discussed the history of TFTR and the most recent program achievements including results of DT operation, neutron measurements and alpha physics. The goals set for TFTR in 1976 have been met and, in several areas, exceeded. An important observation was confirmation that confinement in DT plasmas is better than that in pure deuterium due to an expected, but poorly understood, mass effect. There will now be an additional year of testing to explore D-T confinement enhancement and higher power operating regimes.

Steve Rosen felt that the term "helium ash" should be avoided: the fusion community has adopted an unfortunate nomenclature since the word "ash" gives rise to negative connotations. In fact, helium is a naturally-occurring, non-radioactive benign gas that we use in the Goodyear blimp and in balloons we give to children as toys.

TFTR operates with limiters which are made of carbon fiber composite (CFC) tiles aligned on the inboard side of the plasma. Some discussion and explanation of the nature of limiter operation, and of the anticipated greater efficiency that would arise from the use of a divertor, ensued. Magnetic confinement of the plasma is opposed by pressure-driven diffusion. As the plasma expands, first it brushes up against the tiles that comprise the limiter. This evoked a discussion of the alignment requirements for these tiles. In TFTR, the alignment tolerance requirement is ~1.5 mm with respect to the magnetic field, but it is the nature of CFC's that misalignments tend to be self-correcting.

One recent improvement in TFTR has been the installation of a cryogenic distillation plant for tritium processing, designed and fabricated by Canadian Fusion Fuels Technology Project. The plant has four distillation columns that have a very low tritium inventory. The system works very efficiently despite the fact that there is only a 1 K difference in boiling points between hydrogen, deuterium, and tritium.

Some impressive neutron measurements have been made at TFTR. Neutron yields agree with theoretical calculations, accounting for beam-beam, beam-plasma, and plasma-plasma reactions.

Alpha-particle measurements using charge-exchange processes were described. One of the more serious concerns with alpha reaction product generation is TAE (toroidal Alfvén eigenmode) instabilities stimulated by high-energy alphas. The phenomenon was observed in a single, high-power test shot. Further investigation is needed to reproduce and verify its existence and, should this be the case, to explore the use of density profiles to suppress and control it.

A discussion of the regulatory process for TFTR was stimulated by Jack Kaslow. TFTR experienced a difficult approval procedure for a DOE fusion facility, but public acceptance of the facility has been excellent. TFTR used DOE regulations, rather than those of the NRC, in much the same way that Rocky Flats and Savannah River had. This has proved to be a tortuous, expensive, and time-consuming process. Approximately $40M was spent in unforeseen ES&H retrofits.

An overview of the plan for the U.S. fusion program plan was presented on a single viewgraph. ITER was shown as the "integrator" machine, taking input from TPX and from a Materials Test Facility which has not yet been approved, and leading the way to a fusion Demo. The committee felt that the absence of a materials test facility was a "show-stopper", since the technologies that will be used for ITER will not be attractive to Demo and will certainly not attract funding from the private sector. It was agreed that more attention would be given at a future meeting to the testing facilities that would prepare the program to move into technologies relevant to Demo and to a commercial generating plant. Mark Tillack was tasked to present more detailed information on this subject at the next meeting. The committee viewed this materials research and component development as being critical to the commercial success of the fusion program.

DEMO MISSION AND OBJECTIVES

Dean Robert Conn presented some initial results from the Starlight Demo reactor study, focusing on the mission and goals of the Demo. In order for fusion to be attractive, it must provide safety advantages over fission (since it is unlikely to be less expensive) and cost advantages over solar (since it is unlikely to be safer).

The question of scaling from Demo to a commercial power plant was discussed. No obvious answer emerged from the discussion since the ability to scale depends upon the characteristics of the technology. However, a Demo in the range of 33% to 80% of the size of the follow-on commercial machine was thought to be acceptable. On the other hand, a Demo at one tenth of full-scale was thought not to be acceptable.

The trade-off between Demo cost of electricity and the total cost of the device was discussed. The point was made that a smaller machine, constructed at lower cost, may not be capable of producing electricity economically. Hence, even if the U.S. Government were to pay half the cost of the plant, the utilities would not be interested in it if they had to pay a per-kW-hr penalty. Steve Rosen emphasized that without visionaries, fusion would be a "hard sell". The nature of the present economic infrastructure tends to discourage visionaries; hence, fusion simply must demonstrate a cost advantage.

Waste disposal and the decommissioning of Demo were discussed. It was recommended that Demo should adopt methods of waste disposal which already exist, and not propose new methods which could lead to long drawn out debates. Although a fusion plant should be priced for, say, a 30-year economic life, the licensing of a fusion plant should be for an indefinite period and should not stipulate an expiration date. Since all of the life-limiting in-vessel components can be replaced, artificial restrictions should not be placed on the life of the plant.

DISCUSSION OF MINUTES OF THE PREVIOUS MEETING

A modification to the draft minutes of the previous meeting was discussed at length. This included the cost projections for Demo and concepts for cost sharing and consortia establishment. Aside from the modification, the minutes were approved and Terry Davies was asked to distribute the final approved minutes. In future meetings, the minutes of the previous meeting will be distributed to the committee for approval prior to formal distribution.

DATE OF NEXT MEETING

The committee agreed to hold the next meeting at UC San Diego on February 16-17, 1995. Topics to be included are:

  1. The Safety, Siting and Regulatory Aspects of ITER and DEMO (e.g., Drs. Iotti, Baker and Longhurst),
  2. Mission and Goals of DEMO (Dean Conn and Dr. Najmabadi),
  3. DEMO Testing Needs and Development Pathways (Dr. Tillack)

Appendix I: Meeting Attendees

Tom Burgess			ORNL				615-574-7153
Bob Conn			UC San Diego			619-534-6237
Terry Davies			UCSD				619-534-9830
William Dove			OFE/DOE				301-903-4598
Sheng Guangzhao			SWIP				619-455-4258
Robert Iotti			Raytheon/ITER	
Jack Kaslow			EPRI				603-894-6345
John McCann			Conn Edison			914-734-5566
Dale Meade			PPPL	
Ronald Miller			UCLA/UC San Diego		619-534-7842
Bill Muston 			Texas Utilities			214-812-8407
Farrokh Najmabadi		UC San Diego			619-534-7869
Charles Neumeyer		Raytheon			609-243-2159
Albert Opdenaker		OFE/DOE
Steve Rosen			HL&P				512-972-7138
Glenn T. Sager			General Atomics			619-455-2543
Dai-Kai Sze			ANL				208-252-4838
Mark Tillack			UCSD				619-534-7897
Les Waganer			McDonnell Douglas Aerospace	314-233-8617
Ken Wilson			Sandia				510-294-2497
Clement Wong			General Atomics			619-455-4258

Appendix II: Meeting Agenda

9:30 AM - OCTOBER 13, 1994
1.  INTRODUCTION AND WELCOME                       ROBERT CONN
2.  ITER UPDATE                                    ROBERT IOTTI
3.  DOE UPDATE                                     AL OPDENAKER
4.  ITER ECONOMIC STUDY                            KEN WILSON

LUNCH   12:00 NOON-1:00 PM
5.  "FIRST OF A KIND" START UP EXPERIENCES         LARRY PAPAY
6.  ITER REMOTE MAINTENANCE TECHNIQUES             TOM BURGESS AND
                                                   JOE HERNDON - ORNL
7.  ITER REAL AND REACTIVE POWER REQUIREMENTS      CHARLES NEUMEYER

ADJOURN - 4:00 PM

8:30 AM - OCTOBER 14, 1994

8.  D-T EXPERIMENTS IN TFTR                        DALE MEADE
9.  DEMO MISSION AND GOALS                         ROBERT CONN
10. SUMMARY & SELECTION OF ITEMS FOR NEXT MEETING  ROBERT CONN & STEVE ROSEN
11. DATE AND LOCATION OF NEXT MEETING

ADJOURN - NOON

Top of the page.