ARIES Documents
Utility Advisory Committee Reports
Minutes of the Seventh Meeting (July 31-August 1, 1995, UC San Diego)
Report of the Seventh Joint Meeting of the
Fusion Power Plant Studies Utility Advisory Committee
and EPRI Fusion Working Group
INTRODUCTION
The joint Fusion Power Plant Studies Utility Advisory Committee and EPRI Fusion
Working Group is chaired by Steve Rosen of Houston Lighting and Power Company.
The meeting agenda and list of participants are attached as appendices.
Presentations and discussions are summarized below. The minutes of the previous
(sixth) meeting were approved. Steve Dean presented the Fusion Power Associates
Excellence in Fusion Engineering Award to Prof. Farrokh Najmabadi.
DOE UPDATE
Ira Adler discussed the budget situation in Washington. A $7.5M
recision was approved recently for the FY95 fusion budget.
Congressional fusion budget guidance for FY96 is $229M (House) and
$225M (Senate). The department has been asked to reduce the DOE
budget by $14.1B over the next 5 years. The impact will include a
reduction in the DOE staff from 20,600 to approximately 10,000 by
the year 2000.
Bill Ellis asked where the Office of Fusion Energy might be located
following a reorganization of the DOE. Dr. Adler responded that
combination into an "energy cluster" was proposed, but that it
appears as though OFE will remain within the Energy Research
branch. The idea to eliminate DOE is probably no longer a serious
possibility. The possibility to merge several organizations into a
single cabinet-level science department also is unlikely.
Following a description of the congressional budget process, Jack
Kaslow asked where there might be support for fusion research.
There is not much good news in this area. The strongest support
comes from the New Jersey delegation, in the House Appropriations
subcommittee. One of the most critical members is Mr. Rohrabacher
in the House Authorization subcommittee.
Bill Ellis asked if the guidance for "reduced funding" is meant to be
above and beyond the $229M level. Dr. Adler indicated that it
probably is.
Prof. Conn indicated that the transfer of close-out costs to other
programs should not be considered as a net benefit to the fusion
program relative to the previous budget because this was never
included in previous budgets. With close-out costs, the budget would
be even worse. The real effective purchasing power of the $229M
budget would be $180M with the close-out costs, or $245M without
them (for the Senate language that recommended transfers of NERSC
and other activities previously supported by OFE).
Bill Ellis inquired what is the OFE interpretation of Congress' guidance
to continue to support ITER. The answer is not clear. The numbers
don't add up if all of the Congressional advice is taken. Probably the
guidance is most strongly in favor of maintaining the base program.
Steve Rosen asked if Dr. Adler could comment more on the negative
reaction to the President's Committee of Advisors on Science and
Technology (PCAST) report by our ITER partners. Dr. Adler declined
to respond at this time.
Bill Muston inquired whether the ITER mission and objectives
includes anything about the schedule. The answer is no.
PRESENTATION TO PCAST
Steve Rosen summarized his presentation to PCAST and indicated
that he spoke as a representative of the joint committees and as an
individual citizen, and not as an employee of Houston Lighting and
Power Company. He emphasized the three criteria that would have
to be met by a successful fusion power plant and corresponding
Demo: Economics, Public Acceptance, and Regulatory Simplicity.
PCAST PANEL SURVEY
Prof. Conn added his welcoming remarks to the UAC and indicated
that Dennis McCloud (TVA) will continue as a member of the
committee and will participate in the future.
The committee must consider its future role and whether it will
continue to operate. Prof. Conn indicated that the committee's impact
has been substantial, and believes continued participation would be
beneficial. Due to uncertainties in the program, the committee
should wait to decide on its future. He suggested they continue and
discuss options at the next meeting.
Steve Rosen noted a citation to the UAC in the Fusion Safety
Standard, and indicated that the group should consider whether or
not their position was being accurately represented (see below). He
also suggested adding agenda items to this meeting to discuss ideas
on how this group might react to the current budget situation, and to
discuss the future of the group.
Dr. Miller asked if Prof. Conn might comment on the reaction of the
PCAST to the speech by Rosen. However, all PCAST meetings were
confidential, so that he could not comment.
Jack Kaslow asked how strong is the conviction in the PCAST that we
need a new energy source. The PCAST panel is composed of
members very familiar with the subject of energy needs, including
international issues. They had very strong convictions on this
matter.
Steve Rosen asked if the committee considered how much the 2025
goal would slip at the $320/yr. funding level. Prof. Conn was not
able to answer that yet.
Dr. Baker asked if PCAST had assumed that the budget would have to
rise from $320M some time in the future. In order to complete the
mission of the program, the funding level would have to increase, but
the time frame exceeds the 10-year planning horizon of the panel.
Bill Ellis asked what is the reaction to the ITER Council decision not to
change the mission of ITER, as compared with the PCAST
recommendation. Prof. Conn noted that the U.S. can't continue with
ITER as currently structured. The current budget projections are
even worse than the PCAST level of $320M.
Larry Papay indicated that we need to express our commitment to go
forward with ITER.
John McCann asked if the recommendation to continue TFTR suggests
upgrades or changes to the machine. Prof. Conn answered that the
$50M/yr. budget is for operating expenses, and does not include
modifications.
Steve Rosen asked if dropping the Technology Phase of ITER would
extend the schedule to reach Demo. Will we need another
intermediate machine? Undoubtedly the answer is yes.
Jack Kaslow asked if we change ITER, then how much of the design
work would have to be redone. Charlie Baker mentioned that ITER
has worked well because each partner came to their own conclusions
that it should be done. The U.S. has told ITER through PCAST that we
can't go forward as planned. The partners need to consider this and
their own situations. They will require some time to digest these
changes and be prepared to talk about them. Bob Conn indicated
that the partners have incorrectly assumed that the PCAST report is
an attempt to change the ITER project. The recommendation to enter
into negotiations with our international partners is not meant to
suggest an outcome. There are several possibilities, including
reduced participation by the U.S. in an ITER program as currently
envisioned.
Larry Papay said that Senator Domenici also felt that a scenario for
reduced US funding in the context of the full ITER project might lead
to the same result as SSC, and that this is a serious concern.
Ira Adler asked if the committee had considered what would happen
if the president does not provide a commitment to fusion. Without
high-level support, the program is likely to continue to slide.
Larry Papay indicated that the budget would probably be at the
$200M level and decline.
John McCann asked if there was any way our ITER partners could
influence our government. Charlie Baker answered that some letters
from high-level people in the international community may be
forthcoming.
Bob Conn indicated that DOE support for the PCAST proposal is
lacking. Without this support, it will be difficult to push through any
commitment to fusion.
John McCann asked if the panel believes that energy supply is a
problem. Prof. Conn indicated that the panel believes the U.S. has a
false sense of security regarding energy, and is also not sensitive to
the concerns of other countries regarding energy security. Energy
has been and likely will be a source of international tension and
possibly wars, and it is in the best interest of the U.S. to consider
energy supply more seriously.
Jack Kaslow asked Ira Adler if he could comment on the long-term
prospects and possibility of more stable funding. Dr. Adler gave a
detailed explanation of the budget process and out-year prospects
for fusion, which are not good.
UPDATE ON ITER ACTIVITY
Dr. Baker noted that the ITER Interim Design Report, Cost Review,
Safety Analysis, and Report on Site Requirements were issued in
June 1995 and will lead to a Detailed Report on these issues planned
for December 1996. He reviewed the status of the technical activities
and distributed detailed documents.
John McCann asked if tritium supply is a pacing factor for ITER. The
need for tritium comes mainly from the "technology phase", which is
far down the road and does not affect the near-term program pace.
Steve Rosen and John McCann asked for elaboration on what are the
real safety concerns for evacuation and what safety systems are
included. Both tritium and activation products are important
considerations. A pressure suppression pool probably would be
included, but safety-quality shut-down systems are not envisioned.
DISCUSSION OF SAFETY REQUIREMENTS
Steve Rosen raised the issue of the UAC work having been referenced
in the fusion safety standard. Some of the statements relating to the
ability of ITER to meet the "no evacuation" requirement were
particularly a subject of discussion. The committee felt it was
important to make their position on this matter clear.
1. The committee reiterated its position of supporting a "no-
evacuation" policy, consistent with favorable safety performance for
fusion as described in the criteria document.
2. The committee is concerned that ITER may set a precedent if it
applies relaxed safety requirements. Future commercial plants may
not be able to make maximum advantage of the essential beneficial
features of fusion if the regulatory structure is somehow established
by ITER.
3. The UAC is reluctant to abandon the safety goals specified in the
criteria document. They do not endorse a "waiver" of the safety
requirements for ITER. Rather, they encourage ITER to attempt to
meet the "no evacuation" goal. They can envision why ITER may
need to relax their requirements. However, commercial power plants
should retain the higher goal.
ITER AND DEMO SITE POWER REQUIREMENTS
Dr. Neumeyer now has a total of six utility responses to his survey,
updating the presentation of previous UAC meetings.
He concluded that the reactive power needed to control the ITER
plasma may be as high as +200 or -100 MW. Steve Rosen
commented that this seems to be a lot of effort to keep the plasma
going. He had thought that, once established, the plasma would burn
more quiescently.
The electric grid on the east coast and west coast of the U.S. is "stiff"
enough to handle ITER loads. The Texas grid probably is not. There
is some question whether Europe and Japan could handle ITER on
their grids. Japan probably would have to build additional capacity.
England, France, and some other countries in Europe probably could
handle it. It depends a lot on the quality of the interconnects ("tie-
lines") and controls on the grid. The possible need/value of on-site
energy storage was discussed.
STARLITE UPDATE
Prof. Najmabadi gave a brief overview of the present status of the
Starlite Tokamak Demo Project, delegating the time slot to
presentations by Dr. Tillack and Dr. Miller.
Dr. Tillack, on the basis of his extended European visit, reported on
the European DEMO blanket Development Programme. The EU
blanket program is well-organized and much larger than the U.S.
program. It supports laboratory R&D efforts in Germany, Italy and
France. The goal of the nearly completed 5-year development effort
is to down-select two out of four blanket options for further
development and testing in ITER. The four options are: (1) He-
cooled solid breeder with Breeder-In-Tube (BIT) configuration, (2)
He-cooled solid breeder with Breeder-Outside Tube (BOT)
configuration, (3) water-cooled with semi-stagnant Pb-17Li Breeder,
and (4) dual (He and PbLi) cooled with flowing Pb-17Li Breeder.
MANET (MArtensitic steel for NET) is the structural material chosen a
priori for all designs. The EU approach is significantly different from
the U.S. approach in that it rolls forward from present knowledge
and anticipated ITER tests. The set of design goals was developed by
an ad hoc group, and is not based on a comprehensive systems
analysis of the requirements. In particular, the EU definition of a
"DEMO" does not include requirements nearly as aggressive as the
Starlite project has defined Ð particularly in the area of economic
competitiveness.
Dr. Miller presented the approach used in the Starlite cost
projections. Distinctions between the costing of the first of a kind
(FOAK) Demo and the commercial power plant include a possible
longer construction lead time, the absence of learning-curve credits,
higher contingency costs, and special arrangements consistent with a
Demo-specific utility-government financial partnership to spread
risk. Cost considerations are used within the project in an iterative
manner to guide the design process toward an optimal tokamak
Demo as reported results interface with the external world of energy
forecasting and policy determination, with implications for the
planning of the magnetic fusion R&D program. A coherent linkage
between the Demo and the subsequent commercial tokamak power
plant is established in response to the present perception of future
energy market requirements and goals.
MATERIALS PROGRAM
Dr. Wiffen gave an extended overview of the U.S. program in
advanced materials and irradiation facilities. Development of low
activation structure material (e.g. V and SiC-composites) are
acknowledged to be important to the future Demo. An accelerator-
based International Fusion Materials Neutron Source (IFMIS) is
undergoing conceptual design with the regime of 14-MeV neutron
flux ~ 2 MW/m2 and fluence ~ 100 dpa in a few years at
70% availability. The program is responsive to several PCAST
priorities.
FUSION FILM PROJECT
Mrs. John DeBello and Michael Bayer of Four Square Productions, Inc.,
a San Diego film production company, presented a status report on
their work-in-progress "STARPOWER," an IMAX-format project on
the subject of fusion.
DATE OF NEXT MEETING
The next meeting of the UAC was tentatively anticipated for
December 4-5, 1995, subject to evolving budget and program
strategy situations then prevailing. There is some interest in
broadening the scope of interest to include Inertial Fusion Energy
(IFE) issues.
Appendix I:
Meeting Attendees
Ira Adler DOE 301-903-3347
Charles Baker UCSD/ITER 619-534-4971
Robert Conn UCSD 619-534-6237
Terrence Davies UCSD/ITER 619-534-9830
Steve Dean FPA 301-258-0545
William Dove DOE/OFE 301-903-4598
Bill Ellis Raytheon 212-839-3398
Tom James UCSD/ITER 619-534-6544
Jack Kaslow EPRI 603-894-6345
Grant Logan LLNL 510-422-9816
John McCann Con Edison 914-734-5566
Wayne Meier LLNL 510-422-8536
Ronald Miller UCSD 619-534-7842
Bill Muston TU Services 214-812-8407
Farrokh Najmabadi UCSD 619-534-7869
Charles Neumeyer Raytheon 609-243-2159
Larry Papay Bechtel 415-768-0275
Steve Rosen HL&P 512-972-7138
Pete Skrgic Allegheny Power 212-336-4320
Dai-Kai Sze ANL 708-252-4838
Mark Tillack UCSD 619-534-7897
Lester M. Waganer McDonnell Douglas Corp. 314-233-8617
Bill Wiffen DOE/OFE 301-903-4963
Clement Wong General Atomics 619-455-4258
Appendix II:
Agenda
Joint Meeting of Fusion Power Plant Studies Utility Advisory Committee
(FPPSUAC)
and EPRI Fusion Working Group
July 31-August 1, 1995
University of California, San Diego
Monday, July 31, 1995
9:30 AM Introduction and Welcome Robert Conn (UCSD)
9:15 AM Approval of Minutes of February 16-17, 1995 Meeting
9:30 AM DOE Update I. Adler (DOE)
10:30 AM Presentation to PCAST S. Rosen (HL&P)
11:00 AM PCAST Fusion Panel Summary R. Conn (UCSD)
LUNCH - 12:00 NOON-1:00 PM
1:00 PM PCAST Fusion Panel Summary (Continued) R. Conn (UCSD)
2:00 PM Update on ITER Activity C. Baker (UCSD)
3:00 PM ITER & Demo Site Power Requirements II S. Rosen/
W. Ellis/C. Neumeyer
3:30 PM Materials Program: Facilities Used and Needed B. Wiffen (DOE)
4:30 PM Four Square Productions - IMAX Film Project "Starpower"
ADJOURN - 5:00 PM
Tuesday, August 1, 1995
9:00 AM Materials Program: Facilities Used and Needed
(Continued) B. Wiffen (DOE)
10:00 AM Starlite Update F. Najmabadi (UCSD)
11:00 AM Discussion and Meeting Summary
a. Selection of Items for Next Meeting
b. Date and Location of Next Meeting
ADJOURN - NOON
Top of the page.
|